Which of the following is not a milestone highlighted in the construction period?

Study for the Printreading BIM Test. Prepare with comprehensive questions, detailed answers, and insights into the BIM process. Score high on your exam!

In the context of construction milestones, the process typically includes significant events that indicate progress through the project timeline. The milestones often include critical phases like substantial completion, notice to proceed, and final acceptance, all of which represent specific achievements in the project lifecycle.

Substantial completion is a key milestone that signifies that the project is sufficiently complete to be used for its intended purpose, while the notice to proceed marks the official start of construction activities. Final acceptance indicates that the project has been completed to the satisfaction of the owner or client and meets the contract requirements.

The notice to bid, however, represents an early project phase related to soliciting contractors for bids before the actual construction begins. It does not reflect a milestone achieved during the construction period itself, making it distinct from the other options, which signify progress or completion in the project after construction has commenced. Understanding this distinction highlights the importance of recognizing when specific milestones occur in the overall timeline of a construction project.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy